This is one we've been meaning to post for a while, but something else always seemed to intervene.
In BMG Monroe I, LLC v. Village of Monroe, No. 22-1047 (Feb. 16, 2024), the U.S. Court of Appeals for the Second Circuit affirmed the dismissal of a statutory and constitutional challenge to the Village's .
The court did so on the basis of the surviving part of the Williamson County ripeness requirement, that the government has taken a definitive position on whether it will allow some development of the plaintiff's land under the challenged regulations.
BMG wanted to build 181 homes, so it developed plans for a mix of uses across several parcels, and development of related infrastructure like roads and a community center. This "did not conform to the zoning codes of the Village and Town." Slip op. at 4. The Village and Town were ok with the proposal, however, provided BMG "satisfied certain conditions" such as the look and feel of the buildings, and other architectural style points. Slip op. at 6. Conditional use approvals followed. Eventually, all looked good and the Village and Town granted conditional final approvals.
But when BMG submitted applications for the building permits on several of its lots, the building inspector balked, asserting the architecture and design were off and not what the conditions required. Permits denied. BMG chased administrative appeals to the Zoning Board of Appeals for some -- but not all -- of the lots. The ZBA eventually denied the filed appeals, concluding that indeed, the construction plans were not in conformity with the conditions on those lots.
Having exhausted its administrative remedies on some but not all of the lots, BMG sued. There wasn't a takings claim (BMG's claims included section 1983, Fair Housing Act, and equal protection), but the district court nonetheless applied Williamson County to dismiss the complaint as unripe.
The Second Circuit affirmed. BMG had not received the Village's "final decision" denying development. But wait, you say...I thought that you said that BMG lost the ZBA appeal? That's usually enough, isn't it? Yes, it did do that, but it didn't chase an appeal on all of the lots. Thus, "BMG's failure to obtain a decision from the ZBA 'leaves undetermined the permitted use of the property in question[.]'" Slip op. at 12 (citations omitted).
BMG responded: the reason we didn't chase a ZBA appeal on those other lots was that doing so would have been futile. And we did get final approvals and ZBA denials on the other parcels in the group, so isn't that enough? No, according to the Second Circuit, rejecting the argument that "[i]n essence, BMG argues that its otherwise-unripe claims relating to Lots 1, 2, and 3 can hitch a ride on the ripeness of its claims relating to Lots 45 and 46." Slip op. at 13.
And it didn't matter anyway because even those lots on which BMG chased and lost its ZBA appeals are not ripe because (you guessed it), BMG didn't also seek a variance. Slip op. at 14. Apparently, the Second Circuit sees a variance as some kind of super appeal after ZBA denial. And didn't BMG already get a "variance" (also known as a conditional use permit)?
But that wasn't enough:
We conclude that after the ZBA affirmed the Village Planning Board’s finding that BMG’s construction plans did not comply with previously agreed-upon conditions, BMG was then required to “submit[] at least one meaningful application for a variance” to the Village Planning Board or ZBA to see whether it could apply clustering techniques in the multi-family district while using the new rear elevation, roof pitch, and siding materials.5 See id. Put simply, the SEQRA Findings provided the terms BMG had to abide by in order to depart from the normally applicable land-use restrictions in the Town and Village. As a result, if BMG wished to alter those conditions, it first had to seek another variance before proceeding to federal court. Cf. Southview Assocs., Ltd. v. Bongartz, 980 F.2d 84, 98–99 (2d Cir. 1992) (holding that, even where “the Board ha[d] denied[] . . . one application,” developer still faced burden of establishing that “submission of another application would be futile” (emphasis added)).
Slip op. at 17.
And finally, didn't Pakdel change the ripeness/futility standards? Not at all, according to the Second Circuit. See slip op. at 19. The more things change, the more they stay the same, no?
What's that old adage? If at first you don't succeed, try and try again? We know that in land use, that means as long as the government says it is willing to "clarify" or "change" its decision (something it almost always asserts it is able and willing to do), a court will very likely never hold it to task. Planning authorities know this, and as a consequence are hardwired to almost never say no, and only "no, but..." or "maybe."
Until the Supreme Court wakes up to this dynamic, nothing is likely to change.
BMG Monroe I, LLC v. Village of Monroe, No. 22-1047 (2d Cir. Feb. 16, 2024)